Guess what?! We are on schedule to wrap up the majority of our construction by May 1. We will be working on WiFi and the overall look past May 1, up until we open for the Angie’s List Grand Prix of Indianapolis.

New seats 2

New seats

Penthouse

  • The last of the seats were installed Tuesday
  • Elevator inspections are underway
  • Gutter downspouts are being installed
  • Railings are being painted

HTC 2

HTC 1

Hulman Terrace Club

  • Exterior painting is ongoing
  • Foodservice equipment is being installed
  • Carpet installation is wrapping up
  • Televisions are to be installed next week
  • Suite equipment is to be installed next week
  • General clean-up is underway
  • Furniture (tables, chairs and trash receptacles) to be installed next week

Gate 1

gate 1 2

Gate 1

  • Landscaping is ongoing
  • Commemorative bricks are being installed
  • Gates are being installed
  • Fencing is being finalized
  • General clean-up is underway
  • Lights installation is wrapping up

Tags

About The Author

Samantha Gray

I enjoy engaging and informative social content and providing our fans with a great online experience. As the Social Media Strategist for the Indianapolis Motor Speedway, I would love to hear your feedback on our digital presence. Leave comments and let us know how we're doing. Follow @IMS on Twitter and 'Like' Indianapolis Motor Speedway on Facebook.